Adam Greenland’s Post

View profile for Adam Greenland, graphic

Project Manager at CORBYN CONSTRUCTION LIMITED

Great progress from the team in the last two weeks. 9 slab pours in 10 days with 1100 metres of concrete poured. 16 floor slipform completed, dismantled and removed from site. Well done to the whole team, keep up the good work!